Caltrans scheduled one-way traffic control on Highway 1 in Montara to begin the week of September 28. It runs from 8:30 a.m. to 3:30 p.m., Monday through Friday. That leaves two stretches of the weekday outside the work zone. The first is before 8:30, and Sage Bakehouse, Taqueria El Timón and SamTrans Ride Plus all start at 7 a.m. The second begins at 3:30, half an hour after La Costanera opens its happy hour. Montara's posted hours had this shape before the cones went up. While the repair lasts, they also happen to frame the hours when the highway is narrowed.

What Caltrans Is Doing Between 11th and 13th

The work is a slope repair on northbound State Route 1 between 11th and 13th Streets. According to the Caltrans project advisory, the work includes erosion repairs and slope protection in the affected areas. To keep traffic moving, Caltrans planned temporary railing near 11th Street. The agency says it will monitor conditions and may adjust traffic control while the project runs.

Caltrans expects to finish by November. It also notes that all work depends on weather and the schedule can change. The September 25 advisory is still the only public notice on this project, so November is a target, not a promise. For the day of a trip, Caltrans points drivers to QuickMap and 511 for live conditions.

The work schedule matters as much as the location. One-way control applies only on weekdays and only between 8:30 and 3:30. Evenings, early mornings and weekends are outside it.

The 7 a.m. Side of the Window

Three Montara services start at 7 a.m., and each gets an hour and a half before the work zone opens.

Sage Bakehouse at 8455 Cabrillo Highway serves pies, pastries and coffee. Its own site lists it as open seven days a week, 7 a.m. to 6 p.m. Visit Half Moon Bay also lists it as a Montara bakery and café.

Taqueria El Timón at 1400 Main Street announced its opening for "this Friday, November 14," with a Mexican-fusion menu for dine-in or takeout. It now posts hours of 7 a.m. to 10 p.m. daily. Its address is on Main Street, not Highway 1, and that matters below.

SamTrans Ride Plus is the newest of the three. Effective August 2, 2026, SamTrans added Moss Beach and Montara to its Half Moon Bay Ride Plus service area and moved the daily start time to 7 a.m., according to the agency's schedules and service changes page. For a household that wants to stay off the highway during the work hours, early trips now have a transit option that Montara did not have last summer.

Gherkin's completes the morning list. The sandwich shop at 171 7th Street lists sandwiches, salads and breakfast items. Its site does not post Montara hours, so check with the shop directly before planning around it.

The 3:30 Side of the Window

At the other end of the workday, La Costanera opens its happy hour at 3 p.m., Tuesday through Friday, and runs it until 6. The Peruvian restaurant sits above Montara State Beach. Its happy hour falls only on weekdays, and it overlaps the last half hour of one-way control before running past it.

Here is La Costanera's schedule as posted on its site this spring. Confirm before going, since hours can change by season:

Service Days Hours
Happy hour Tuesday to Friday 3 to 6 p.m.
Lunch Thursday to Sunday 11 a.m. to 4 p.m.
Dinner Tuesday to Sunday 4 to 9 p.m.
Grab-and-go counter Friday to Sunday 11 a.m. to 6 p.m.

On Saturdays and Sundays, lunch and the grab-and-go counter both run with no lane control on the highway.

Guests bound for the Point Montara Lighthouse grounds at 8800 Cabrillo Highway should know the property is reservation-only, according to HI USA. The hostel's FAQ asks visitors to check in at the office before walking the grounds. Only registered guests may enter the hostel itself, and HI does not currently offer hostel-run tours.

A Weekday by the Posted Hours

Put the sources together and a Tuesday through Friday this fall lines up like this:

  1. 7:00 a.m. Sage Bakehouse, Taqueria El Timón and Ride Plus all start.
  2. 8:30 a.m. One-way traffic control begins on northbound Highway 1 between 11th and 13th Streets.
  3. 11:00 a.m., Thursday and Friday La Costanera's lunch service opens.
  4. 3:00 p.m. Happy hour starts at La Costanera.
  5. 3:30 p.m. Lane control ends for the day.
  6. 4:00 p.m. La Costanera's dinner service begins, running until 9.
  7. 6:00 p.m. Sage Bakehouse closes. Taqueria El Timón stays open until 10.

Mondays follow the same work hours. La Costanera serves no happy hour or dinner that day.

Main Street Is Getting Its Own Work, on Its Own Notice

The highway repair isn't the only roadwork in town this fall. San Mateo County Public Works is running its 2026 Pavement Preservation Project in the Montara and Miramar areas. The work covers pavement repairs, microsurfacing, new traffic striping and pavement markings. The County's August update put the expected construction start at August 11. Its September update reported that pavement repair had begun and that microsurfacing was scheduled to start in mid-September.

This project works differently from the Caltrans job. The County does not post a fixed daily window. Instead, it gives affected residents two days' notice before any surface treatment that needs a full road closure. The project page offers email updates for anyone who wants notices directly.

The paving also ties into a longer plan. On its Midcoast Multimodal Trail page, the County says the Parallel Trail becomes a mix of sidewalk and on-street bikeway on Main Street from 11th to 2nd Street. It also says Public Works will add a shared bikeway as part of a 2026 pavement rehabilitation project. The County is still looking for money to close the feasible sidewalk gaps on that stretch. The segments from 14th to 11th and from 2nd to 1st still need funding for feasibility studies. South of town, the trail's completed Southern Segment has run from Coronado Street to just past Mirada Road since 2022.

This means Montara is being rebuilt in two layers. Caltrans is working on the highway slope, while the County is working on the local streets that serve as the town's off-highway route.

Where the Next Round of Road Decisions Gets Made

The MidCoast Community Council holds its regular meeting on Wednesday, October 14, at 7 p.m. The meeting is hybrid. According to the posted agenda, items include an informational update on SamTrans Coastside services and a County update on the Moss Beach State Route 1 and San Carlos project. The County is also asking the council to support a trail-gap project on Carlos Street.

The County's presentation describes the Carlos Street proposal as a 2,400-foot Class 1 path from Highway 1 to Etheldore Street. The County is pursuing grant funding for environmental work and design, with an application due October 30. That makes it a funding request, not a construction start. The same document says the environmental document for the Moss Beach SR 1 project is now expected in late 2026. The County anticipates an in-person open house at Farallone View Elementary and will take written comments for at least 30 days after release.

Farallone View also hosts two dates that don't depend on any road schedule:

  • Saturday, October 24, 8 a.m. to noon: Recology's Montara and Moss Beach bulky-item recycling day at Farallone View School. It ends at noon or when the trucks are full, whichever comes first.
  • Saturday, December 5, 10 a.m. to 2 p.m.: the Farallone View Holiday Bazaar, open to the public, with local vendors, student performances, crafts and food.

Both fall on Saturdays, when Highway 1 has no lane control. If Caltrans finishes on its target, the highway will be fully open again before the bazaar.

A slope repair on Highway 1 and new paving on Main Street can change which streets carry a Montara household's daily trips, and when a showing or a moving truck can get through easily. If you're timing a sale or a move on the Coastside this season, Stephanie Nash can talk through how this fall's road work fits your calendar. Let's Connect.

Stephanie Nash smiling in a white blouse with a pendant necklace.

Stephanie Nash

About The Author

For more than three decades, Stephanie Nash has been one of the Peninsula’s most trusted and proven real estate advisors, serving Woodside, Portola Valley, Atherton, Redwood City, Emerald Hills, San Carlos, Half Moon Bay, and the surrounding communities from Burlingame to Los Gatos.

Born and raised on the Peninsula, Stephanie brings true insider knowledge of the region; its micro-neighborhoods, school corridors, country-property enclaves, and the lifestyle features that make this area so coveted: sunny weather, an easygoing spirit, hiking trails, large-parcel retreats, ocean-view hillsides, and world-class food and culture.

A career built on experience, ethics, and results

Stephanie began her real estate career in 1987 working in local title companies before becoming the assistant to a top-producing agent. She earned her real estate license in 1991, and since then has built a reputation as a solutions-driven, ethical, and steady negotiator who guides clients through every complexity of a California transaction.

Her track record includes everything from luxury estates to rural acreage to trust and estate sales, including the successful sale of a 500-acre property, a transaction requiring extensive due diligence, jurisdictional navigation, and long-term strategy.

Nationally recognized performance

Stephanie has been recognized multiple times by RealTrends as one of the “Best Agents in America,” most recently in 2024; an honor reserved for the top tier of agents nationwide based on verified production.

Expert Witness in Real Estate Matters

In addition to client representation, Stephanie now serves as a retained Expert Witness in California real estate cases—including valuation disputes, fiduciary sales, marketing standards, agent performance, disclosure practices, and industry-standard care.

What clients rely on her for

Whether you are buying, selling, downsizing, expanding, or handling a trust/estate sale, Stephanie offers:

  • Deep regional expertise across multiple Peninsula micro-markets

  • Strong negotiation skills grounded in fairness, strategy, and consistent communication

  • Experience in complex transactions (trusts, estates, multiple-heir negotiations, title defects, rural land issues)

  • Compassionate guidance rooted in decades of hands-on client service

  • Unmatched availability and responsiveness

Clients praise her listening skills, honesty, and ability to navigate even the most emotional or complicated sale with clarity and professionalism.

A life built around community and care

Stephanie is deeply grateful for her family, her life on the Peninsula, and the meaningful relationships formed through her work. 

Work With Stephanie

Stephanie respects residential real estate’s dual role as a personal investment and chief financial one. Whether you are buying or selling a home, it will likely be one of the largest financial decisions you make. Stephanie will be with you every step of the way to expertly guide you.

Let's Connect